The expanded list of installation photo deliverables associated with the DOE Solar Access Program will be maintained, however, it should be noted that there are additional requirements based on specific manufacturers.
For the complete list of photo deliverables, see the standard Install (M1) Photo Documentation article.
Mounting System/Roof photos:
Attachments - Flashing & Sealant
Rail with Opto/Micro mounted + EGC + Wire management
Complete array with rail trimmed
Micro inverter model
Under array wire management
Tilt (one per unique roof pitch)
Junction boxes (cover off)
Photo of one PV Module serial number per site
PV Module label
Any project with a tree removed should have comprehensive photos showing the stump and surrounding area in relation to the structure with solar attachment.
Electrical photos:
Consumption CTs & Cell kits/cell modems required
Inverter(s) / Combiner box
Switches / Disconnects (fused only)
Main breaker & Busbar rating
Point of interconnection - close up & pull back
Pull back of BOS
Solar equipment serial labels
Completed wiring, including grounding/bonding in relevant enclosures
Commissioning
Fully commissioned, communicating, and producing system
Ensure all relevant screenshots from the commissioning app are uploaded
Screenshots should show a fully operational systems with all devices paired, active communication, reporting production and consumption including cellular connection signal.
Provide PCS settings, if applicable
Storage Photos
Transfer switch enclosure
Battery CT location and direction
Battery component legible serial labels
Pullback photos showing completed battery(s) location
Ensure you follow Battery communication wire instructions as they differ per manufacture
Installation of bollards in compliance with PR fire code, where applicable, would be prudent here
Production & Consumption Meter Requirements
All LightReach projects require production & consumption monitoring
SolarEdge inverters need an integrated revenue grade meter (RGM) with consumption CT ports, and additional CTs
Enphase systems require additional CTs for consumption monitoring
Rooftop Junction Boxes
Conductors landed in terminal block on DIN rail, grounding landed in ground bar and exposed conductors exiting box are protected from exposure by panel
If DIN rail not used, push-in or crimp connectors connectors preferred over wire nuts
Connector/lock ring used to transition into box from attic.
Watertight strain relief fittings used to transition from box to PV array.
Box is cut into shingles providing a clean look, and preventing water intrusion
If the junction box is more than two inches outside of the array, hard pipe to it.
Weep holes to prevent condensation and water retention in boxes
Best Practices - BOS
Conduit bodies reduce amount of conduit required and provides a much cleaner look
Duct seal and weep holes to prevent condensation and water retention in boxes
Prioritize Bottom Entry when possible
Top entry voids some warranties








