Submission packages include five key sections for the DOE program, with a number of sub sections included into them. Projects should be submitted when the installation is complete (Defined as POST EPC quality audit.)
How to Use This GuideThis guide is organized into main sections (A - E), each containing several numbered sub-sections. You can find these sections in the right-hand menu to quickly access the information you need. Guide Structure:
Image ViewingIn each section, where applicable, you will find a tab with the option "Click to view images." Use this feature to see graphical examples that complement the documentation. If you are unsure where to find something, use the right-hand menu to quickly locate relevant information. |
Category | Sub-section |
(A) Project Site |
|
(B) Roof Work |
|
(C) Ground Electrical |
|
(D) Energy Storage |
|
(E) Project Completion |
|
General & Best Practices
Collect Clear Documentation of conditions on site (before and after photos) prior to starting work
Please take pictures only after the work has been completed. Pictures taken while the wiring has not been completed can cause confusion and delays in the review process.
When taking photos it is recommended to take a close up and a clear pullback
M1 requirements are geared toward ensuring key principles of system production, safety, and customer experience.
These requirements and standards are a combination of topics derived from LightReach installation standards, Generac Manufacture Guidelines, and Program Monitor Audit Criteria. This information is intended to support, not replace, code requirements and manufacturer recommendations.
Please reference the AVL Knowledge page for specific information on equipment used - DOE: Approved Vendor List
Ensure that installations are meeting all Site Eligibility and Solar Ready Repair Requirements
(A) Project Site
Requirement | Description | Examples |
Site Information |
| |
Site Conditions |
|
|
Existing Site Damage (if applicable):
Any pre-existing damage or conditions should also be documented, evidence of current or historical pooling on the roof, including but not limited to roof leaks or rusted rebar visible from inside, biological growth, cracked tar or sealant, bare concrete (un-coated) roofs, etc. Generally anything that could potentially be a workmanship liability in the project work area.
Documentation helps reduce unnecessary service evaluations
Existing Code Violations (if applicable):
It is the responsibility of all parties to make all reasonable efforts to ensure the home is solar ready (meaning all existing electrical equipment between the inverter output and the utility is suitable for connection and operation of the new system).
-AND- identify any pre existing issues with the home’s electrical system and either remediate those issues or escalate.
(B) Roof Work
Component Identification
Requirement | Description | Examples |
Distinct serial of PV module used |
|
|
PV module data label - Pull back of panel label on site |
|
|
PV Link map with serial numbers |
|
Rooftop in Progress
Requirement | Description | Examples |
|
Close up of Attachment - Sealed & Installed | Racking Systems without Flashing - Photos should highlight properly applied Sealant within or around the attachment
Racking Systems with Flashing - Provide photos showing properly installed flashing to manufacturer specs, along with sealant application
Click for details
|
|
|
Rail Design |
Click for details
|
| |
Rooftop Equipment - Rail, PV Links, and EGC are Installed |
Click for details
|
| |
Torque Tool Verification |
|
|
|
Vent Pipe Relocation - |
Click for details
|
|
|
Finished Arrays
Requirement | Description | Examples |
Completed Array |
Click for details
|
|
PV Mounts, Attachments, Torque Marks |
Click for details
| |
Tilt - Measured on Array |
Click for details
|
|
Under Array |
Click for details
|
Electrical Photos - Non BOS
1. Module Connectors:
Requirements
Picture of a Field Made Staubli MC4 Connector that has been installed with a legible label
Additional Details
Connectors are rated for use and connections are properly made per manufacturers guidelines
All Module Connectors need to be Staubli Branded components
Connector Glands are required to be torqued to manufacture specifications
2. Junction, Pull, and Outlet Boxes:
Requirements
One example of Conductor Termination showing proper technique
One open photo of each junction box with completed wiring and bonding. Include closeup of the conductor terminated, or the transition through conduit
Take pictures of the roof conduit supports that show the mechanical attachment method used. (Tapcon visible)
Additional Details
All enclosures are installed so that the wiring contained in them can be rendered accessible directly or by displacement of components secured by removable fasteners and connected by a flexible wiring system.
J box should not have any more than 2" of exposed conductors outside of the array. Any exposed conductor over 2" will have to be installed in a conduit.
Ensure the roof junction boxes and LBs have a neoprene seal.
Always add weep holes at the lowest point in JBoxes or Conduit bodies.
J-boxes align with the top of the rail and do not make contact with the underside of the module.
JBoxes cannot be secured to the Iron Ridge Rail System with self tapping screws, ONLY approved Iron Ridge BONDING HARDWARE can be used
T-BOLT - (BHW-TB-03-A1)
Square Bolt - (BHW-SQ-03-A1)
See more details on this process here.
Ensure Conduits are supported and positive attachment (fasteners) can be identified.
JBoxes cannot be secured to the Iron Ridge Rail System with self tapping screws, non penetrative attachments need to be used.
(C) Ground Electrical
Electrical Component Identification
Requirement | Description | Examples |
Inverter Label |
| |
Automatic Transfer Switch (ATS) label |
| |
Battery Information |
|
Electrical Equipment
1. Trenching (if applicable):
Requirements
Document any needed trench work performed . Trench depth must adhere to NEC 300.5.
Additional Details
Document any needed trench work performed . Trench depth must adhere to NEC 300.5.
2. Inverter(s):
Requirements
Collect photos of all internal Inverter wiring, ensuring that production CTs are clearly visible.
Ensure that all communication devices are photographed and installed correctly.
Additional Details
Inverter Wiring
Wiring (including clear photos of breaker ratings, production CT, and consumption CT Terminals) /Generac lower cabinet showing RGM
Production CTs: Installed inside the DC wiring section. Grouping both L1’s in a single clamp and both L2’s in a single clamp. “Source” label facing the AC terminal blocks.
Cellular Kit & Antenna Installed?
Comms Cables
CT and ATS Cat 5 (or Cat 6) cables are tested and securely connected to the CT port and ATS port respectively.
Inverters must be equipped with internal revenue grade metering (RGM).
Torque markings are correctly applied on all terminals
NEC labeling required for M2.
3. Consumption Meter:
Requirements
Close up of CT terminal lugs with the correct CT phases landed in the correct terminals. CTs on service feeders, with direction of CTs visible. (Inside the ATS or upstream)
Additional Details
All projects require consumption monitoring equipment installed to manufacturer specifications.
If CTs are physically unable to be installed, please include photo context showing the situation (e.g. busbars in meter/main panels where CTs physically cannot be placed, or split service setups where whole home consumption is not possible. These situations are not common).
4. Electrical equipment - New Loads Panel:
Requirements
Document the sub panel installation, close ups and pullbacks.
Additional Details
ALL Loads are labeled per the Customer Education and LOAD LABELING Guidance
High Priority: Green
Medium Priority: Yellow
Low Priority: Red
5. Point of Interconnection:
Requirements
Close up of actual POC parallel lugs, distribution blocks, breakers, or wire terminations.
Pullbacks of the panel surrounding the POC demonstrate the complete wiring and labeling. (Trough grounding)
Additional Details
Correct Inverter OCP size Used? (2P 40A) - All Solar Access Projects are designed with 40A breakers.
Need to document the service panel in which the interconnection is being performed
Document close up of back feed breaker (size clearly legible)
The PV system AC output overcurrent device is properly sized and installed in accordance with NEC and/or manufacturers recommendations.
For PV systems that feed a panelboard, PV system overcurrent protection installed in the correct location within the panelboard.
6. Conduit and Raceways:
Requirements
The conduit and raceways installed on site are shown in photos, including the trough grounding and weep hole placement.
Additional details
Where inside buildings, PV system DC circuits that exceed 30 volts or 8 amperes shall be contained in metal raceways, in type MC cable that complies with 250.118, or in metal enclosures.
Where conduit is installed it is BONDED, rated for use (size, rating, and type), properly mounted/supported per NEC Code requirements, and sealed when transitioning to conditioned space.
Raceways enter enclosure(s) (Inverters, Disconnects, ATS, Batteries, etc) below energized components and have been sealed and conductors are arranged to direct water away from energized components.
For all enclosures used, manufacturer install instructions must be followed, any modifications to the methods of securement, opening of lids, or positioning of deadfronts will void the warranty and result system rework.
Equipment Standards
1. Main Breaker Height:
Requirements
Clear photo showing the measurement of the main breaker from grade.
2. Battery Breaker Height:
Requirements
Clear photo showing the measurement of the battery breaker from grade.
Additional Details
Disconnecting Means should not exceed 6 feet 7 inches (2.0 meters) above the floor or working platform.
2. Equipment Locations (Pull Back):
Requirements
Photo(s) showing the complete BOS equipment installed - Ideal photos are pullback photos showing full context of the BOS area - If in a location where the battery could be damaged by a vehicle, the battery is protected by approved barriers.
Additional Details
Battery is located and positioned to meet all NEC and Manufacturers requirements and provisions have been made to properly protect and, if need, to vent any possible gasses from the storage device.
If installed in a garage or other location where the battery could be damaged by a vehicle, the battery is protected by approved barriers.
Barriers such as a bollards shall be so arranged and of such strength as to prevent damage.
All equipment requiring access is installed with a minimum 3' workspace clearance provided, or otherwise as guided by NEC 110.26 equipment located away (>10' from any roof drains). If unable to avoid drain locations, water flow must be re-directed. Blocking water spouts is not an acceptable method of redirecting water flow.
3. Secondary Disconnects (Optional):
Requirements
Secondary disconnect to meet height requirement. AC Disconnects-Interior wiring and terminations Pull back - Switches/Fuses/Disconnects/Breakers - close up of rating
Additional Details
Disconnects are rated for their locations, properly installed. Disconnecting means is located in a readily accessible location either on the outside of a structure or inside nearest the point of entrance of the system conductors.
4. Enclosure Workmanship:
(Inverters, Disconnects, ATS, Batteries, etc.)
Requirements
Collect photos of all Electrical Enclosures installed or modified during the project (close ups and pullbacks).
Photos of enclosures with properly fitted and secured dead fronts.
Additional Details
Enclosures are not prevented from closing by the placement of conduit or wires.
No metal shavings or debris in enclosure(s)
Deadfront Requirements
Cover material requirements
Water resistant
Thermally Rated
Free of sharp edges and areas that can an individual interacting with the cover or damage conductors when in place
No sharp edges or pointed fasteners on any equipment
All energized parts must be inaccessible and covered by a deadfront that requires a tool to access
Disconnecting means must be accessible without tool
Grounded metal components
Tap and thread on all fasteners is required for a metallic fix this ensures proper grounding to cabinet
Non metallic medium addresses concerns of item being properly grounded
5. Conductors and Terminations:
Best Practices followed for torque and terminations - adhering to manufacturer's specifications and marked by installation team. Minimal bare conductor at terminations.
Standard building conductors are used, No pinched/damaged conductors or tight bends (actual radius will vary based on conductor type and size, typically >5x the outer diameter of the conductor).
Conductors entering or exiting a conduit body or box have a strain relief?
6. Grounds and Neutrals:
Details
Grounding conductors are clearly marked and identified, properly sized, following standard coloring code for AC or DC conductors, and grouped in raceways or trays.
Equipment grounding conductor(s) (EGC) are properly sized per NEC requirements. Array EGC is at least 6 AWG when located outside of raceway (NEC 250.120(C)).
All metal parts of racking, raceways, cables, enclosures are grounded and equipment connections are free from non-conductive coatings to ensure proper electrical continuity and effective path to ground. Array bonded to mounting system and/or EGC.
Neutral Conductor requirements are followed, Bonded to GEC in Disconnect ONLY and separated elsewhere in the system.
7. Labeling
Requirements
Document ALL labels, signs, and warning labels (Inverters, Combiners, Disconnecting Means, all Points of Interconnection, etc.)
Additional Details
All boxes, enclosures are closed with their respective screws.
System Labeling should match the plansets and all label values should be neat and legible.
8. Interior Electrical (If Applicable):
Requirements
All Interior Electrical work needs to be code compliant and documented for quality assurance, pullbacks of work completed.
Additional Details
Where inside buildings, PV system, and battery DC circuits that exceed 30 volts or 8 amperes shall be contained in metal raceways, in type MC cable that complies with 250.118, or in metal enclosures. Anytime metal raceways are used, grounding devices will need to be added to one end of the raceway (ground lugs).
(D) Energy Storage
Equipment Standards
1. Automatic Transfer Switch (ATS):
Requirements
Provide photos of internal ATS Wiring capturing torque marks and correct comm cable placement.
Additional Details
Torque markings are properly applied
ATS wired according to manufacturer's instructions (DC Conductors, EGC, and Comm Cables) and properly terminated.
ATS installation meets all required safety considerations per NEC 110.27 (Guarding of Live parts) and mitigating hazards while servicing or maintaining equipment.
Cat5 cable landed at ATS control and CT terminals. (May use CT terminal block instead)
Serial label or monitoring access.
2. Backup Battery:
Requirements
Close up photos of ALL battery wiring
Additional Details
All ESS OCD and Conductors match the as designed plan and are sized appropriate to service.
ESS installation meets all required safety considerations per NEC 110.27 (Guarding of Live parts) and mitigating hazards while servicing or maintaining equipment.
Disconnecting means should not exceed 6 feet 7 inches (2.0 meters) above the floor or working platform.
Module Spacers are required installation
Battery power harness and communication cables are properly connected, and loop jumpers are connected for M3, M4, and M5 configurations (take close up photos).
3. Battery Supports:
Battery Foot Bracket requires at least 4 structural fasteners.
Supports shall be installed no more than 5” above the floor or working platform.
Install instructions specify that batteries installed outdoors or elevated off the ground require the Foot Bracket.
4. Rapid Shutdown Switch / E Stop:
Requirements
Provide photos of Shutdown Switch location and internal wiring
RSD wire color
Additional Details
Rapid shutdown switch installed properly, wired to the inverter and battery STOP (located outside if equipment is inside).
Where needed, a properly installed and wired disconnecting means (E Stop) has been installed.
(E) Project Completion
Commissioning
1. Site voltage
Requirements
Photograph voltage measurement at main breaker
Additional Details
When commissioning the system, collect Site Voltage Measurements. It is important that voltage measurements are taken before and after installation to obtain at least 2 data points and have a better chance of identifying voltage issues on the property earlier in the process.
2. Commissioning
Requirements
Generac screenshots should show inverter & CTs enabled, networking connected to Cellular, as well as Grid profile set to PREPA 2024 and External transfer timeout set to 300 seconds, as well as islanding screen to confirm the step was done.
Photo of Operational System connected to the internet and reporting to PWRfleet.
Additional Details
Commissioning of the system as well as an Islanding test should be completed prior to leaving the site. The system should be fully operational with all PV Links "Making Power", Battery screen displaying the "Charging" status, active communication, reporting production and consumption data including cellular connection signal.
Battery Backup Profile set to CLEAN
Grid profile set to PREPA 2024 and External transfer timeout set to 300 seconds.
System has been re-energized and is operational.
(F) Project Completion
Closeout
1. Cleanup
All boxes, enclosures are closed with their respective screws.
Absolutely no trash, materials or equipment/tools left behind.
The inverter does not indicate any arc or ground faults, or any other error messages.
2. Installation Related Damage
Document any signs of installation related damage that may need to be corrected post install.
3. Solar Ready Repairs
Requirements
IF performed, document all Solar Ready Repairs. Before and After Photos are required.
Site Survey uploaded to the account as SITE ASSESSMENT DOC type.















































































































